Apestar Design Standard

The minimum rules for every solar and battery system we design, quote or install. They were written after real failures in the field, in plain language, so a customer can check them too.

Download the PDF

01

Refill

The panels must refill an empty battery in one day

The array must carry the day’s load and put a fully drained battery back in one day of sun. If it cannot, the design is rejected.

Panels needed (kWp) = (daily load + usable battery) ÷ 4.5 sun hours × 1.3 weather margin

Usable battery is 80% of its rated size. The 1.3 margin covers dust, heat and cloudy days.

Worked example. A home uses 5.65 kWh a day and has a 5.1 kWh battery (4.1 kWh usable). Needed: (5.65 + 4.1) ÷ 4.5 × 1.3 = 2.8 kWp, so five 620 W panels. Three panels (1.86 kWp) give about 6.3 kWh a day against 9.7 kWh needed: the battery empties on one bad night and never recovers. That system was installed in Ibadan in September 2026. This rule exists so it cannot happen again.

Why: sizing panels from the daily load alone quietly assumes the battery is already full.

02

Start

At least four panels in series on a 48 V system

The panel string must stay above the inverter’s start voltage when the panels are hot.

A typical 48 V inverter needs about 120 V to start charging. Panel voltage drops as panels heat up: on a hot roof the cells run near 70 °C, roughly 10–15% below the label figure.

Panels in series (620 W)Voltage, coolVoltage, hot roofStarts charging?
3~124 V~108 VNo — only in bright sun
4~166 V~145 VYes
5~207 V~180 VYes, comfortably

This is a voltage limit, not a wattage limit: adding panels side by side does not fix it. The wiring (for example “5S1P”: five in series, one string) is written on every quote and handover record. The string’s open-circuit voltage on a cold morning (10 °C) must also stay under the inverter’s maximum.

03

Match

Match the panels to what the battery can take

A single 5 kWh lithium battery accepts roughly 2.5 kW of charge. Once the array satisfies Rules 1 and 2, a second battery helps the customer more than extra panels. We recommend storage before more modules.

04

Reserve

Commission with a reserve, never at the floor

  • Battery type set to lithium, with the battery and inverter confirmed to be communicating.
  • Low-battery cut-off set at 20%, never the factory default. A system allowed to run to its own protection point strands the customer and wears out the battery.
  • Before leaving site, the charge level shown on the inverter must match the battery’s own screen. If they disagree, communication is not really working.

05

Record

Every installation gets a handover record

Each system is handed over with a certificate the customer keeps, carrying a unique registration number and a QR code. It lists:

  • Location, captured on site
  • Serial numbers of the inverter and every battery; panels by model and count
  • Panel, inverter and battery size, and the wiring
  • Photos of the array, wiring, battery and inverter label
  • The checks against Rules 1, 2 and 4
  • The technician, and the customer’s own confirmation

Never weaken these rules to hit a price. If a customer cannot afford a compliant system, we make the battery and the load expectation smaller together, so the panels can still refill the smaller battery. An under-built system turns one price objection into months of complaints.